Raising London Circuit Main Works (A170) - 公共プロジェクト現場
-
26th 9月 2023, PRE START
-R con digger loading 3 x 8 wheelers with material from behind existing retaining wall, material will be stockpiled on the west.
- bridge demo to continue with metro under asbestos conditions
- multiple asbestos removal exclusion zones
- continue back filling/storm water works
- continue site setup ACCESS/FENCING/ERSED ETC
- positive comms UHF30
- no access to site without UHF radio
- obey site VMPs and standard road rules
- exclusion zones for all high risk works.
- float movements -
15th 6月 2023, Pre Start
Drainage, ongoing site wide
Under-bore launch pit excavation at West Gate, keep clear of area unless involved in the activity
Loading out ACM, T&D's
NW Clover Import and place, level, compact clean fill, Rigids
Telstra AMC
SW clover Temp Ramp construction, stay clear
現在の現場の天気
最終更新日時: 3:21
温度: -1C (アプリ -3C)
風速: 0KMH
最大風速: 6KMH @0:21
午前9時からの雨: 0.0mm
最低気温: -2C @2:36
最高気温: 13C @14:47 2026/07/08
突風: 0KMH
最大突風: 7KMH @0:21
観察場所 - Canberra, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
予測 - 木曜日, 9 7月
Morning frost. Partly cloudy.
分: 1C マックス: 13C
降雨の可能性: 10%パーセント
予測場所 - Canberra, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
明日 - 金曜日, 10 7月
Morning frost. Shower or two.
分: -1C マックス: 12C
降雨の可能性: 60%パーセント
予想降雨量: 0 に 2mm